top of page

Trenchless vs. Open-Cut Construction in Municipal Tenders: How to Specify the Right Method

  • Nitika Sharma
  • Jul 6
  • 9 min read

Key Takeaways 

• Open-cut per-foot installation cost is often lower, but total project cost frequently favours trenchless once restoration, traffic control, and excess soil management are factored in. 

• Ontario’s O. Reg. 213/91 imposes escalating safety requirements for open-cut excavations beyond 1.2 metres deep, including shoring, engineered support systems, and professional engineer involvement at 6 metres. 

• Municipal tenders that default to open-cut without requiring method justification from bidders risk higher total costs and longer construction timelines on urban road and crossing projects. 

• Trenchless methods (HDD, pipe bursting, CIPP) are not universally better. Shallow, short-run installations in open ground with no surface infrastructure to protect remain strong candidates for open-cut. 

• Tenders should require total-cost-of-ownership breakdowns, not just unit pricing, so procurement teams can evaluate the real cost of each method.



Trenchless vs open cut trenching is not a question of which method is better. It is a question of which method fits the site. On developed urban roads, crossings, and congested utility corridors, trenchless methods typically deliver lower total project cost because they eliminate the restoration, traffic control, and excess soil costs that inflate open-cut budgets. On greenfield sites with no pavement to protect, open-cut remains faster, simpler, and cheaper. The tender documents should force that analysis, not default to either method by habit. 

Municipal tenders for underground utility work default to open-cut trenching more often than the project conditions warrant. The reason is straightforward: open-cut is familiar, its unit costs are easy to compare, and most tender templates were written before trenchless methods became commercially viable for routine installations. That default costs municipalities money, time, and public goodwill on projects where a trenchless approach would have delivered a better outcome. The reverse is also true. Specifying trenchless on a project where open-cut is the practical choice adds cost and complexity for no benefit. The decision should be driven by site conditions, total project cost, and construction impact, not by habit or assumption. 

This guide breaks down where each method wins, where tender documents fail to capture the real cost picture, and what municipal procurement teams should require from bidders to make the right call. 


What Separates These Two Approaches on a Real Job Site 

The technical difference is simple. Open-cut means digging a trench, installing the utility, backfilling, compacting, and restoring whatever was on the surface. Trenchless methods, whether horizontal directional drilling (HDD), pipe bursting, or cured-in-place pipe (CIPP), install or rehabilitate utilities with minimal excavation, typically limited to entry and exit pits or access points. 

The operational difference is where it matters. On an open-cut urban road project, the construction zone expands to include traffic detours, excavation shoring, spoil management, compaction testing, base reinstatement, asphalt restoration, and line painting. The disruption footprint is large and the timeline extends well beyond the actual pipe installation. On a trenchless project, the pipe goes in beneath the surface infrastructure. The road stays open. The restoration scope shrinks to two small pits instead of a full road cut. 

Neither of those descriptions makes one method better. It makes them suited to different conditions. 




Trenchless vs Open Cut Trenching: Side-by-Side Comparison




Where Open-Cut Still Wins 


Open-cut is the right method when the conditions favour it, and no amount of trenchless enthusiasm changes that. 

Shallow, short-run installations in open ground with no pavement or surface infrastructure to protect are faster and cheaper with a backhoe and a trench box than with an HDD rig. New subdivision construction is the clearest example: the roads are not yet paved, the grades are being established, and the contractor is already moving earth. Trenching water, sanitary sewer, and storm drainage into open subgrade is the most efficient approach.

Gravity sewer installations where grade tolerance is critical also favour open-cut. While HDD can achieve the precision needed for gravity flow, the grade verification process is simpler and more transparent in an open trench where the invert is visible and adjustable. 

Projects where multiple utilities share a single corridor, such as a combined water, sewer, and hydro trench, benefit from one excavation rather than multiple trenchless setups. 

The deciding factor is restoration cost. When there is nothing expensive to remove and replace on the surface, open-cut’s lower per-foot installation cost translates directly to lower total project cost. 


Where Trenchless Methods Pull Ahead 

Trenchless methods deliver the most value when the surface and subsurface are already developed. 

Road crossings are the most common example. An HDD bore beneath a four-lane arterial avoids the road cut permit, traffic control plan, pavement demolition, granular base removal, compaction testing, base reinstatement, asphalt paving, and line painting that an open-cut crossing requires. The installation cost per foot

is higher, but total project cost is often lower because every ancillary line item from the open-cut scope disappears. 


Rail crossings carry even more weight. Rail operators require flagging, track protection plans, and operational windows that compress the available construction time. HDD eliminates the need to open the rail bed entirely. 

Congested utility corridors, particularly in established urban areas where gas, hydro, telecom, and water lines occupy the same right-of-way, present significant strike risk during open-cut excavation. HDD, combined with hydrovac potholing [INTERNAL LINK: Hydrovac Excavating service page] every 6 to 15 metres along the bore path to verify existing utility positions, reduces that risk by keeping the work below the existing utility layer. 


Environmentally sensitive areas, including waterway crossings and sites with contaminated soils, also favour trenchless. HDD under a watercourse avoids in-stream work permits under the federal Fisheries Act, while avoiding excavation in contaminated ground eliminates the soil characterization and disposal costs triggered by O. Reg. 406/19. 

Other trenchless methods serve different applications. Pipe bursting [INTERNAL LINK: Water and Sewer Construction service page] replaces deteriorated water and sewer mains without excavating the full alignment. CIPP rehabilitates existing sewer pipe from the inside, extending its service life without excavation. 

The Decision Framework: Choose Open-Cut When... Choose Trenchless When... 

Choose open-cut when: 

• The alignment is short, shallow, and in open ground with no pavement, landscaping, or active surface infrastructure to protect. 

• Gravity sewer grade tolerance is tight and the invert needs to be visible for verification during installation. • Multiple utilities will share a single corridor and can be installed in one trench. 

• Bulk earthwork is already in the project scope (e.g., new subdivision grading). 

Choose trenchless when: 

• The alignment crosses a paved road, rail corridor, waterway, or environmentally sensitive area.

• Surface restoration would cost more than the installation itself. 

• The utility corridor is congested with existing underground infrastructure and strike risk is high. 

• Traffic control duration and cost are significant line items (busy arterials, school zones, hospital access roads). 

• The project site includes potentially contaminated soils that would trigger O. Reg. 406/19 obligations if excavated. 

When the answer is not obvious, the tender should require bidders to propose a method with written justification and total-cost-of-ownership pricing. That forces the analysis onto the parties who know the site best. 

The Cost Comparison Municipal Tenders Get Wrong 


Most municipal tenders evaluate bids on unit price: cost per linear metre of pipe installed, cost per cubic metre of excavation. That comparison consistently favours open-cut because the per-unit installation cost is lower. 

The problem is that per-unit installation cost is not the same as total project cost. An open-cut road crossing includes a long list of ancillary costs that do not appear in the trenching line item but appear elsewhere in the bid, or emerge as change orders during construction. 

Consider a straightforward 80-metre water main crossing under a two-lane municipal road. The open-cut bid may show a lower cost for the pipe installation itself. But the total scope includes pavement removal and disposal, excavation with shoring (required under O. Reg. 213/91 at depths beyond 1.2 metres), dewatering if the water table is high, backfill and compaction testing to Ontario Provincial Standard Specification (OPSS 401) requirements, granular base reinstatement, asphalt paving, traffic control for the duration of the open excavation, and site restoration per OPSS 492. On a busy municipal road, traffic control alone can run for weeks, and it is typically one of the largest ancillary line items on the project. When those costs are stacked up, the total open-cut price frequently exceeds what the same crossing would have cost by HDD. 


An HDD installation for the same crossing eliminates most of those ancillary costs. The surface stays intact. Traffic control is limited to the entry and exit pit locations. Restoration covers two small excavations, not 80 metres of road rebuild. 

Municipal tenders that require total-cost-of-ownership breakdowns, including restoration, traffic control, excess soil management, and schedule-driven costs, give procurement teams the data they need to evaluate methods accurately. 

What to Specify in the Tender Documents 

Procurement teams can build better tenders by requiring five things from bidders, regardless of which method is proposed.

First, require method justification. Do not default to open-cut in the tender specifications. Instead, describe the scope (alignment, diameter, depth, soil conditions, surface conditions) and ask bidders to propose the method with a written rationale. Bidders who understand the site will propose the right method. Those who do not will reveal themselves. 

Second, require utility verification to a defined quality level. Reference ASCE 38-22 and specify Quality Level A (test hole exposure) or Quality Level B (surface geophysical designating) for existing utilities along the alignment. For open-cut bids, this reduces strike risk during excavation. For HDD bids, potholing along the bore path is already standard practice. 

Third, require compliance documentation matched to the method. Open-cut bids should include an excavation safety plan compliant with O. Reg. 213/91, identifying soil classification, protective system design, competent person assignments, and access/egress provisions. HDD bids should include a frac-out contingency plan and bore path profile. 

Fourth, require total-cost-of-ownership pricing. The bid form should separate installation cost from restoration cost, traffic control cost, and excess soil management cost so evaluators can compare total project cost across methods, not just unit prices. 

Fifth, require a locate plan referencing the Ontario Underground Infrastructure Notification System Act, 2012. All bidders should confirm that Ontario One Call requests will be submitted in accordance with the Act, that private utility locating will be performed separately (Ontario One Call only covers member-owned infrastructure), and that locate validity will be maintained throughout the construction period.

Ontario-Specific Considerations 

Ontario’s regulatory framework adds cost and complexity to open-cut that does not apply equally to trenchless methods. 

O. Reg. 213/91 (Construction Projects) governs excavation safety under Part III, ss. 222–242. Protective systems are required for any excavation deeper than 1.2 metres where workers will enter. Soil must be classified into Types 1 through 4, with the protective system matched to the type. At 6 metres depth, a professional engineer must design the support system. Spoil must be kept at least 1 metre from the excavation edge. These requirements are mandatory and enforced by the Ontario Ministry of Labour, Immigration, Training and Skills Development (MLITSD). 

O. Reg. 406/19 (On-Site and Excess Soil Management) governs excavated soil leaving the project site. Open-cut projects generating more than 2,000 m³ of excess soil require registration, assessment of past uses, and potentially soil characterization sampling. This adds cost and administrative time that trenchless methods largely avoid, since they generate minimal excavated material. 

Ontario Provincial Standard Specifications govern municipal construction quality. OPSS 401 covers trenching, backfilling, and compacting. OPSS 450 covers HDD installation. OPSS 492 covers site restoration. Tenders referencing these specifications ensure consistent quality expectations regardless of method. 

The Ontario Underground Infrastructure Notification System Act, 2012, requires all excavators to contact Ontario One Call before breaking ground. As of May 2024, administrative penalties can be issued for non-compliance, including excavating without valid locates. Locates are generally valid for 30 days from the

date of completion, meaning longer open-cut projects may require re-location during construction. This is a scheduling and cost factor that trenchless installations, with their shorter active construction windows, are less likely to encounter. 

Frequently Asked Questions 

Q1. Is trenchless always more expensive than open-cut? 

No. Trenchless methods carry a higher per-foot installation cost, but total project cost on urban road crossings, congested corridors, and environmentally sensitive sites is frequently lower because surface restoration, traffic control, and excess soil costs are reduced or eliminated. 

The comparison depends entirely on what is above and around the alignment. On a greenfield subdivision with no pavement to remove and no traffic to manage, open-cut will almost always cost less. On an established urban arterial with asphalt, curbs, sidewalks, and active traffic, the ancillary costs of open-cut often exceed the premium for trenchless installation. 

Q2. Can trenchless methods handle gravity sewer installations? 

Yes, but with conditions. HDD can achieve the grade precision required for gravity sewer flow, tracked by sonde/walkover locating systems that provide real-time depth and alignment data. However, the grade verification process is less direct than in an open trench where the invert is visible. 

For short gravity sewer runs with tight tolerances, open-cut provides more straightforward grade control. For longer crossings or alignments beneath developed surfaces, HDD with precision grade tracking is a viable and often preferred alternative. 

Q3. What should a municipal RFP require for method selection? 

The RFP should describe the project scope and site conditions, then require bidders to propose a method with written justification. The bid form should separate installation cost from restoration, traffic control, and soil management costs so evaluators can compare total project cost. Bidders should also submit compliance documentation: an O. Reg. 213/91 excavation safety plan for open-cut proposals, or a frac-out contingency plan and bore path profile for HDD proposals. 

Q4. Does Ontario One Call locate all underground utilities? 

No. Ontario One Call coordinates locates for member-owned infrastructure, primarily public and franchised utilities such as gas, hydro, water, and telecom. Private utilities, including site services beyond the utility demarcation point and privately owned infrastructure, are not covered. Municipal tenders should require bidders to identify and locate private utilities separately, typically through a private utility locating contractor using electromagnetic locating or ground-penetrating radar. 



Comments


bottom of page